Analisa Perbandingan Waktu dan Biaya Antara Metode Pelat Bondek dan Halfslab pada Gedung Apartemen di Sidoarjo

Al Fajr, Muhammad Naufal (2021) Analisa Perbandingan Waktu dan Biaya Antara Metode Pelat Bondek dan Halfslab pada Gedung Apartemen di Sidoarjo. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111710013053-Undergraduate_Thesis.pdf] Text
10111710013053-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 October 2023.

Download (22MB) | Request a copy

Abstract

Pekerjaan struktur pelat merupakan salah satu bagian dari proses kontruksi yang membutuhkan waktu yang lama dalam proses pembuatannya. Banyak perusahaan kontruksi yang masih menggunakan metode konvensional yaitu dengan pengecoran di tempat (cast in situ). Cara konvensional ini tersebut membutuhkan waktu yang lama, biaya yang lebih besar, dan tidak ramah lingkungan karena masih menggunakan
bekisting dari kayu yang menghasilkan limbah. Sehingga perusahaan penyedia jasa kontruksi berkompetisi untuk mencari alternatif metode kontruksi tersebut. Diantara metode alternatif tersebut ialah metode halfslab dan pelat bondek.
Pada penelitian ini akan dilakukan perbandingan sistem precast
halfslab dan bondeks pada proyek Apartemen Tamansari tower beatus
Sidoarjo dari segi waktu dan biaya. Metode yang dilakukan di proyek
tersebut adalah sistem konvensional/cor di lokasi. Pada tugas akhir ini
direncanakan alternatif berupa precast halfslab dan bondeks. Data analisa
yang diperlukan untuk perbandingan dua sistem ini adalah data sekunder
yaitu berupa RAB, time schedule, gambar pelaksanaan, peralatan kerja. Perencanaan waktu menggunakan sistem penjadwalan PDM. Sedangkan untuk perencanaan biaya menggunakan perhitungan analisa dari data lapangan, observasi, maupun harga satuan Sidoarjo. Adapun analisis perbandingan sistem precast halfslab dengan pelat bondeks didapatkan hasil untuk sistem precast halfslab membutuhkan waktu pelaksanaan 172 hari dengan biaya sebesar Rp 12.288.065.000 sedangkan pelat bondeks membutuhkan waktu pelaksanaan 210 hari dengan biaya sebesar Rp 11.412.214.000
================================================================================================
Slab structure work is one part of the construction process that
requires a long time in the manufacturing process. Many construction
companies still use the conventional method, namely by casting in situ
(cast in situ). This conventional method takes a long time, costs more, and
is not environmentally friendly because it still uses formwork from wood
which produces waste. So that construction service providers compete to
find alternative construction methods. Among these alternative methods
are the halfslab and bondek plate methods
In this study, a comparison of the halfslab and bondeks precast
systems in the Tamansari Beatus Sidoarjo Apartment project will be
carried out in terms of time and cost. The method used in the project is a
conventional/cast system on site. In this final project, an alternative is
planned in the form of precast halfslab and bondeks. The analytical data
needed for the comparison of these two systems is secondary data in the
form of RAB, time schedule, implementation drawings, work equipment.
Time planning using PDM scheduling system. Meanwhile, for cost
planning, it uses analytical calculations from field data, observations, and Sidoarjo unit prices.
As for the comparative analysis of the precast halfslab system with bondeks plates, the results obtained for the halfslab precast system requires 172 days of implementation at a cost of Rp 12.288.065.000 while
Bound deck take 210 days of execution at a cost of Rp 11.412.214.000.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Perbandingan, Halfslab, bondeks, biaya, waktu Comparison, Halfslab, bondeks, Cost , Time
Subjects: T Technology > TA Engineering (General). Civil engineering (General) > TA418.9 Composite materials. Laminated materials.
T Technology > TA Engineering (General). Civil engineering (General) > TA660.P55 Underground pipeline design, construction and management
T Technology > TA Engineering (General). Civil engineering (General) > TA681 Concrete construction
T Technology > TA Engineering (General). Civil engineering (General) > TA683 Precast concrete construction. Prestressed concrete construction.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: Muhammad Naufal Al Fajr
Date Deposited: 27 Aug 2021 00:38
Last Modified: 27 Aug 2021 00:38
URI: http://repository.its.ac.id/id/eprint/90686

Actions (login required)

View Item View Item