Pratama, Bintang Samudra (2021) Manajeman Pelaksanaan Konstruksi Pada Pekerjaan Pembangunan Proyek Duplikasi Jembatan Kepet, Kab. Tuban Dengan Menggunakan Building Information Modelling (BIM). Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
10111710010096-Undergraduate-Thesis for D4 program.pdf - Accepted Version Download (21MB) | Preview |
Abstract
Proyek Duplikasi Jembatan Kepet yang terletak di BTS. Kota Tuban-Pakah KM. Sby 95+860 berada di Jl. Nasional No.1 Kepet, Tunah, Kec. Semanding, Kab. Tuban. Proyek ini merupakan salah satu rencana pembangunan Balai Besar Pelaksanaan Jalan Nasional VIII Jawa Timur yang dilaksanakan pada tahun 2020. Proyek ini memiliki panjang total mencapai 525 meter yang terdiri dari panjang jembatan 35 meter dengan lebar jembatan 10 meter serta memiliki oprit jembatan 490 meter. Tujuan dilaksanakan pembangunan ini yaitu untuk mempercepat aksesibilitas sehingga depat mengurangi kemacetan atau penumpukan kendaraan di Jl. Nasional No.1 Kepet, Tunah, Kec. Semanding, Kab. Tuban, karena memiliki jembatan lama yang sudah berumur, akses jalan yang sempit dan meminimalisir kecelakaan yang sering terjadi di area jembatan hingga tanjakan yang terdapat di sepanjang Jl. Nasional Kepet. Dengan adanya permasalah – permasalahan ini maka, perlunya pembangunan jembatan baru yang dibangun sisi barat jembatan lama serta pembangunan proyek jembatan tersebut harus diikuti dengan proses pengerjaan yang efisien dan tepat waktu.
Perhitungan biaya dan waktu pada proyek ini dilakukan dengan menghitung volume tiap item pekerjaan, produktifitas alat berat dan pekerja, material kebutuhan, upah pekerja, serta perhitungan biaya alat berat dan biaya material berdasarkan harga terbaru pada lokasi proyek tahun 2020 di kota Tuban, sehingga dari perhitungan tersebut didapatkan Rencana Anggaran Pelaksanaan (RAP) dan dapat menghitung bobot masing-masing item pekrjaan. Lalu penyusunan jadwal pelaksanaan menggunakan program bantu MS Project. Dari perhitungan tersebut didapatakn hasil akhir berupa Kurva-S. Kemudian permodelan menggunakan Building Information Modelling (BIM) untuk pembuatan metode pelaksanaan konstruksi yang diterapkan dilapangan. Dengan implementasi BIM ini maka pekerjaan suatu proyek dapat meningkatkan efisiensi waktu, biaya, dan meminimalisir human error atau kesalahan desain serta lebih mudah mengetahui resiko pada pelaksanaan konstruksi yang merupakan manfaat utama penerapan teknologi BIM.
Hasil yang didapatkan dari penelitian ini adalah waktu pembangunan jembatan yaitu selama 173 hari atau setara dengan 6 bulan, serta biaya untuk pelaksanaan pembangunan proyek sebesar Rp.15.871.507.773 . Biaya total yang diperoleh ini belum termasuk dengan overhead&profit . Maka pada proyek Duplikasi Jembatan Kepet, kab. Tuban ini biaya overdead&profit Rp.1.587.150.777, sehingga didapatkan biaya total keseluruhan proyek yaitu Rp.17.458.658.000 terbilang tujuh belas milyar empat ratus lima puluh delapan juta enam ratus lima puluh delapan ribu rupiah.
Kata kunci : BIM, biaya pelaksanaan, waktu pelaksanaan dan kurva S.
====================================================================================================
Kepet Bridge Duplication Project located at BTS. City of Tuban-Pakah KM. Sby 95+860 is on Jl. National No.1 Kepet, Tunah, Kec. Semanding, Kab. Tuban. This project is one of the plans for the construction of the Central Java VIII National Road Implementation Center which will be implemented in 2020. This project has a total length of 525 meters consisting of a bridge length of 35 meters with a bridge width of 10 meters and a bridge oprit of 490 meters. The purpose of this development is to accelerate accessibility so as to reduce congestion or vehicle buildup on Jl. National No.1 Kepet, Tunah, Kec.
Semanding, Kab. Tuban, because it has an old bridge that is already old, narrow road access and minimizes accidents that often occur in the bridge area to the incline along Jl. Kepet National. Given these problems,the need for the construction of a new bridge built on the west side of the old bridge and the construction of the bridge project must be followed by an efficient and timely process.
The calculation of costs and time in this project is done by calculating the volume of each work item, productivity of heavy equipment and workers, material needs, workers' wages, as well as the calculation of the cost of heavy equipment and material costs based on the latest price standards in 2020 in the city of Tuban, so that from these calculations an Implementation Budget Plan (RAP) is obtained and can calculate the weight of each work item. Then the preparation of the implementation schedule using the MS Project assistance program. From these calculations, the final result is an S-Curve. Then the modeling uses Building Information Modeling (BIM) for the implementation of the construction method applied in the field. With the implementation of BIM, the work of a project can improve time, cost, and efficiency efficiency. and minimize human error or design errors and make it easier to know the risks in construction implementation which are the main benefits of implementing BIM technology.
The results obtained from this study are the time for the construction of the bridge which is 173 days or the equivalent of 6 months, and the cost for the implementation of the project construction is Rp. 15,871,507,773. The total cost obtained does not include overhead & profit. So in the Kepet Bridge Duplication project, kab. Tuban costs overdead & profit Rp. 1,587,150,777, so that the total cost of the entire project is Rp. 17,458,658,000, which is seventeen billion four hundred fifty eight million six hundred and fifty eight thousand rupiah.
Keywords: BIM, implementation costs, implementation time and S curve.
Item Type: | Thesis (Undergraduate) |
---|---|
Uncontrolled Keywords: | BIM, biaya pelaksanaan, waktu pelaksanaan dan kurva S., implementation costs, implementation time and S curve. |
Subjects: | T Technology > T Technology (General) > T56.8 Project Management |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D4) |
Depositing User: | Pratama Bintang Samudra |
Date Deposited: | 09 Sep 2021 06:11 |
Last Modified: | 26 May 2024 00:35 |
URI: | http://repository.its.ac.id/id/eprint/91869 |
Actions (login required)
View Item |