Analisis Waktu Penyelesaian Pekerjaan Erection and Welding pada Outer dan Inner Shell Propane Tank T-201 dengan Simulasi Monte Carlo dalam Proyek Pembangunan Terminal LPG Refrigerated Jawa Timur (Tahap-1)

Andiko, Yachya Rifqi (2022) Analisis Waktu Penyelesaian Pekerjaan Erection and Welding pada Outer dan Inner Shell Propane Tank T-201 dengan Simulasi Monte Carlo dalam Proyek Pembangunan Terminal LPG Refrigerated Jawa Timur (Tahap-1). Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 04311840000092-Undergraduate_Thesis.pdf]
Preview
Text
04311840000092-Undergraduate_Thesis.pdf - Accepted Version

Download (4MB) | Preview

Abstract

Pemerintah Indonesia melalui PT. Pertamina (Persero) berencana membangun fasilitas dalam rangka pemenuhan kebutuhan LPG Indonesia dalam sebuah proyek bernama “Proyek Pembangunan Terminal LPG Refrigerated Jawa Timur”. Saat ini proyek tersebut sedang dalam proses konstruksi tahap-1 oleh PT. Wijaya Karya (Persero) yang membentuk konsorsium dengan PT. JGC Indonesia, yang kemudian disebut dengan KSO WIKA-JIND. Proyek tersebut memiliki tiga lingkup pekerjaan yaitu sipil, mekanis, dan testing and commissioning yang ditargetkan selesai dalam jangka waktu 30 bulan terhitung dari 01 Oktober 2019 hingga 31 Maret 2022. Menurut Ali et al. (2012) terdapat dampak yang sering terjadi akibat adanya keterlambatan proyek konstruksi, oleh karena itu sangat diperlukan pengaturan waktu yang tepat sehingga proyek dapat berjalan dengan baik dalam mencapai tujuan utamanya. Penelitian ini membahas aplikasi simulasi Monte Carlo dalam mengestimasi waktu penyelesaian proyek dengan menggunakan bantuan program Microsoft Excel. Bagal (2019) menjelaskan bahwa teknik simulasi Monte Carlo merupakan teknik paling layak dan cukup sering digunakan untuk memperkirakan peluang penyelesaian proyek. Ditemukan bahwa data yang digunakan pada simulasi Monte Carlo merupakan data yang didapat pada pengalaman sebelumnya yang kemudian diolah agar dapat memperkirakan probabilitas setiap kegiatan menggunakan distribusi normal. Didapatkan bahwa durasi minimum penyelesaian pekerjaan adalah 322 hari dengan peluang 0,05%, durasi maksimum adalah 389 hari dengan peluang 100%, sedangkan durasi paling memungkinkan adalah 359 hari dengan peluang 80,02%, lalu peluang terjadi keterlambatan atau durasi ekspektasi dilewati adalah sebesar 62,85%. Diketahui pula bahwa apabila terjadi keterlambatan, maka akan memerlukan penambahan manhours sebesar minimal 603, dan maksimal 24896 manhours.
================================================================================================
The Indonesian government through PT. Pertamina (Persero) plans to build facilities to fulfill Indonesia’s LPG needs in a project called “Proyek Pembangunan Terminal LPG Refrigerated Jawa Timur”. Currently the project is in the phase-1 construction by PT. Wijaya Karya (Persero) which formed a consortium with PT. JGC Indonesia. The project is targeted to be completed within 30 months starting from October 1, 2019, to March 31, 2022. According to Ali et al. (2012) there are impacts that often occur due to delays in construction projects, therefore it is very necessary to manage the time so that the project can run well in achieving its main goals. This study discusses the application of Monte Carlo simulation in estimating the project completion time using Microsoft Excel program. Bagal (2019) explains that the Monte Carlo simulation technique is the most feasible technique and used quite often to estimate the project completion probability. The data used in the Monte Carlo simulation is obtained from previous experience then processed to estimate the probability of each activity using a normal distribution. It was found that the minimum duration of work completion is 322 days with a 0.05% probability, the maximum duration is 389 days with a 100% probability, while the most probable duration is 359 days with an 80.02% probability, then the probability of delay is exceeded is 62.85%. It is also known that if there is a delay, it will require additional manhours of at least 603, and a maximum of 24896.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Pekerjaan Erection and Welding, Simulasi Monte Carlo, Waktu Penyelesaian, Completion Duration, Erection and Welding Work, Monte Carlo Simulation
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD61 Risk Management
H Social Sciences > HD Industries. Land use. Labor > HD69.T54 Time management. Scheduling
T Technology > T Technology (General) > T56.8 Project Management
T Technology > T Technology (General) > T57.62 Simulation
T Technology > TA Engineering (General). Civil engineering (General) > TA660.T34 Tanks. Pressure vessels
Divisions: Faculty of Marine Technology (MARTECH) > Ocean Engineering > 38201-(S1) Undergraduate Thesis
Depositing User: Yachya Rifqi Andiko
Date Deposited: 27 Jan 2022 05:33
Last Modified: 05 Jun 2024 04:15
URI: http://repository.its.ac.id/id/eprint/92517

Actions (login required)

View Item View Item