PERHITUNGAN WAKTU DAN BIAYA PELAKSANAAN PROYEK APARTEMEN LAVIZ TOWER LT. 1 – LT. 9 DENGAN MENGGUNAKAN PELAT SISTEM HALF SLAB.

Yuseno, Rendro (2020) PERHITUNGAN WAKTU DAN BIAYA PELAKSANAAN PROYEK APARTEMEN LAVIZ TOWER LT. 1 – LT. 9 DENGAN MENGGUNAKAN PELAT SISTEM HALF SLAB. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111610013045_Undergraduate_Thesis.pdf]
Preview
Text
10111610013045_Undergraduate_Thesis.pdf

Download (18MB) | Preview

Abstract

Sebelum pelaksanaan suatu proyek pembangunan dimulai perlu dilakukan sebuah rencana yang tersusun untuk mengetahui estimasi anggaran biaya dan lama waktu pengerjaan suatu proyek pembangunan tersebut. Perencanaan tersebut dilakukan bertujuan untuk menekan waktu pekejaan dan biaya agar lebih terukur, efisien dan sesuai yang diharapkan. Bangunan yang digunakan untuk tugas akhir terapan ini adalah proyek Apartemen Laviz Tower Surabaya yang terletak di Jl. Mayjen Yono Sowono No.2, PTC Surabaya-Jawa Timur.
Pada Tugas Akhir ini digunakan modifikasi dari pelat konvensional ke pelat dengan sistem half slab. Penggunaan pelat dengan sistem half slab akan berpengaruh pada kecepatan pelaksanaan suatu proyek, karena pekerjaan half slab dapat dikerjakan secara parallel dan tidak membutuhkan waktu pemasangan bekisting pada saat pemasangan half slab dilapangan.
Suatu proyek perlu dilakukan penjadwalan waktu. Penjadwalan tersebut dilakukan sebagai acuan saat pelaksanaan proyek sedang berjalan. Salah satu contoh metode penjadwalan adalah dengan menggunakan PDM (Precedence Diagram Methode). Menurut Soeharto (1999), PDM dikenal adanya konstrain. Satu konstrain hanya dapat menghubungkan dua node, karena setiap node memiliki dua ujung yaitu ujung awal (S) dan akhir (F). Setelah menghitung waktu pelaksanaan maka dilanjutkan dengan menghitung anggaran biaya. Untuk menghitung biaya pelaksanaan suatu proyek bangunan, perlu dianalisis pehihitungannya secara rinci. Menurut soedrajat (1984) terdapat lima hal pokok dalam menghitung anggaran biaya yaitu mulai dari bahan, upah pekerja, sewa pralatan, biaya overhead dan keunntungan.
Berdasarkan hasil analisa diperoleh rencana biaya pelaksanaan untuk pekerjaan struktur pada proyek ini sebesar Rp 17.931.961.568,00 (Tujuh Belas Milyar Sembilan Ratus Tiga Puluh Satu Juta Sembilan Ratus Enam Puluh Satu Ribu Lima Ratus Enam Puluh Delapan Rupiah) dengan waktu pelaksanaan pembangunan proyek selama 66 hari.
===============
==============
Before the implementation of a development project begins it is necessary to make a plan that is structured to find out the estimated budget and length of time for the construction project. The planning is carried out aiming to reduce work time and costs to be more measurable, efficient and as expected. The building used for this final project is the Laviz Tower Surabaya Apartment project located on Jl. Mayjen Yono Sowono No.2, PTC Surabaya-East Java.
This final project uses modification from conventional plates to plates with a half slab system. The use of plates with a half slab system will affect the speed of implementation of a project, because half slab work can be done in parallel and does not require installation of formwork when installing half slab in the field.
A project needs to be timed. The scheduling is done as a reference when project implementation is underway. One example of scheduling method is to use PDM (Precedence Diagram Method). According to Suharto (1999), PDM is known for its constraints. One constraint can only connect two nodes, because each node has two ends, namely the beginning (S) and the end (F). After calculating the implementation time then proceed with calculating the budget. To calculate the cost of implementing a building project, detailed calculations need to be analyzed. According Soedrajat (1984) there are five main things in calculating the cost budget that is starting from materials, workers' wages, equipment rental, overhead costs and benefits.
Based on the analysis results obtained plan implementation costs for structural work on this project is Rp. 17,931,961,568.00 (Seventeen Billion Nine Hundred Thirty-One Million Nine Hundred Sixty One Thousand Five Hundred Sixty-Eight Rupiah) with the project implementation time being 66 days.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Rencana Anggaran Biaya Pelaksanaan, Waktu Pelaksanaan, Pelat Sistem Half Slab.
Subjects: T Technology > TH Building construction > TH11 Builders' and contractors' bulletins. Including prices, permits, etc.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: Rendro Yuseno
Date Deposited: 28 Aug 2020 06:12
Last Modified: 04 Jan 2024 07:11
URI: http://repository.its.ac.id/id/eprint/81590