Metode Pelaksanaan Main Dam Bendungan Tukul Kabupaten Pacitan, Jawa Timur

Suprayogi, Dohri and Yuliansa, Rahmat (2018) Metode Pelaksanaan Main Dam Bendungan Tukul Kabupaten Pacitan, Jawa Timur. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111400000122 - 10111400000139 -Non_Degree.pdf]
Preview
Text
10111400000122 - 10111400000139 -Non_Degree.pdf - Accepted Version

Download (7MB) | Preview

Abstract

Pembangunan waduk tukul kabupaten pacitan ini berfungsi sebagai penyedia air irigasi di daerah kabupaten pacitan dan sekitarnya yang meliputi luas area sebesar 1.070 ha. Pembangunan waduk ini membutuhkan perencanaan metode pelaksanaan yang tepat. Agar pelaksanaan dapat berjalan sesuai dengan target yang diharapkan, maka dibutuhkan instrumen pengendalian yang meliputi teknik pelaksanaan dan produktifitas alat berat untuk mempermuda pelaksanaan pekerjaan.
Karena hal tersebut, kami merancang teknik dalam metode pelaksanaan yang akan digunanakan di lapangan. Teknik-teknik yang akan kami ulas meliputi teknik pelaksanaan dalam pekerjaan tubuh bendungan pada pembangunan waduk tukul yang sekarang dilaksanakan oleh PT. Brantas Abipraya. Alasan kami mengulas teknik-teknik pelaksanaan pada pekerjaan tubuh bendungan pada waduk tukul ini, agar dapat mengoptimalkan kinerja pada pembangunan di lapangan. Dengan menjabarkan teknik pada metode pelaksanaan, kami berharap mendapatkan alternatif baru dalam pelaksanaan di lapangan. Selain itu dalam pengulasan metode pelaksanaan, kami menggunakan jangka waktu penyelesaian yang ditetapkan pihak lapangan yaitu 3 bulan sebagai instrument pengendali waktu untuk mengetahui jumlah alat berat yang nantinya dapat digunakan untuk pertimbangan guna pengefisiensian penggunaan alat berat dari segi quantiti.
Dari perhitungan produktifitas alat berat untuk mendapatkan kebutuhan alat berat yanga akan digunakan, didapatkan kebutuhan alat berat yang terlalu over untuk pekerjaan tiap zona pada tubuh bendungan waduk tukul ini. Hal ini bisa terjadi karena waktu pekerjaan yang ditargetkan terlalu cepat untuk pekerjaan dengan volume kerja yang besar. Dengan penambahan waktu kerja dapat memperkecil kebutuhan akan penyediaan alat berat pada pekerjaan tubuh bendungan ini.
============ Construction of Tukul Reservoir in District of Pacitan district serves as a provider of irrigation water in the District of Pacitan and surrounding areas covering an area of 1,070 Ha. The construction of these reservoirs requires proper planning of implementation methods. In order for the implementation to run in accordance with the expected targets, it is necessary to control the instrument that includes implementation engineering and productivity of heavy equipment to facilitate the implementation.
Because of this, we decided techniques in the method of implementation that will be used in the field of project. The techniques that we will review include implementation techniques in main dam work on the construction of tukul dam that is now implemented by PT. Brantas Abipraya. The reason we review the implementation techniques on the dam body work on this tukul dam, in order to optimize the performance on the development in the field. By describing the technique on the method of implementation, we hope to get a new alternative in the field. In addition to the implementation method, we use a 3-month settlement timeframe as a time control instrument to determine the amount of heavy duty equipment that can be used for consideration in order to make use of heavy duty equipment in terms of quantity.
From the calculation of heavy equipment productivity to obtain heavy equipment needs to be used, we find the needs of heavy equipment that we think is still too much in terms of quantiti. This can happen because the time job is targeted too quickly for work with a large working volume. With the planned addition of working time that is still reasonable, it can be possible to minimize the need for heavy equipment on the work of this dam body.

Item Type: Thesis (Diploma)
Additional Information: RSIS 627.8 Sup m
Uncontrolled Keywords: implementation method; heavy duty equipment productivity.
Subjects: T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Dohri Suprayogi
Date Deposited: 30 Apr 2018 05:38
Last Modified: 21 Jul 2020 07:08
URI: http://repository.its.ac.id/id/eprint/51030

Actions (login required)

View Item View Item