Perhitungan Waktu Dan Biaya Pelaksanaan Pembangunan Gedung Type B1 Rsud Dr. M. Soewandhie Surabaya Dengan Metode Half Slab

Ferdiansyah, Yoga (2021) Perhitungan Waktu Dan Biaya Pelaksanaan Pembangunan Gedung Type B1 Rsud Dr. M. Soewandhie Surabaya Dengan Metode Half Slab. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111710013031_Undergraduate_Thesis.pdf]
Preview
Text
10111710013031_Undergraduate_Thesis.pdf - Accepted Version

Download (20MB) | Preview

Abstract

Penyusunan proyek akhir dengan judul Perhitungan Waktu dan Biaya Pelaksanaan Pembangunan Gedung Type B1 RSUD dr. M. Soewandhie Surabaya dengan Metode Half Slab yang terletak di Jl. Tambak Rejo No. 45-47, Tambakrejo, Kec. Simokerto, Kota Surabaya. Proyek ini dibangun oleh PT. PP (Persero) Tbk yang terdiri dari 2 bangunan utama gedung rumah sakit dengan 10 lantai dan bangunan parkiran dengan 8 lantai. Tetapi karena terkendala oleh COVID-19 proyek ini hanya dibangun 6 lantai di Gedung utama dan 3 lantai Gedung parkiran.
Untuk proyek akhir ini yang ditinjau adalah bangunan utama Gedung rumah sakit mulai lantai 1 sampai dengan lantai dak atap lift yaitu 10 (8 lantai + 2 dak atap) dengan memodifikasi bagian pelat yang sebelumnya menggunakan pelat konvensional menjadi half slab precast. Pekerjaan yang ditinjau hanya struktur atas. Struktur atas meliputi kolom balok, tangga, ruangan linac, dan brachytheraphy yang menggunakan pengecoran in-situ terkecuali pelat yang menggunakan precast. Dalam perhitungan waktu yang ditentukan dengan mengitung volume pekerjaan,produktivitas, durasi, dan kebutuhan sumber daya pada tiap-tiap item pekerjaan. Perhitungan tersebut disesuaikan dengan metode pelaksanaan yang sesuai dan referensi dari literatur yang terkait. Sedangkan dalam perhitungan biaya meliputi harga material, upah pekerja, dan dan harga sewa alat berat yang dihitung menggunakan harga lapangan dan referensi di Surabaya. Sehingga diharapkan dengan penggunaan metode yang tepat, akan menghasilkan perencanaan waktu
iv
dan biaya yang efektif dan efisien dalam pembangunan Gedung Type B1 RSUD dr. M. Soewandhie Surabaya. Hasil akhir dari P akhir ini diperoleh rekapitulasi perhitungan waktu dan biaya pelaksaan, serta kurva S pada proyek pembangunan Gedung Type B1 RSUD dr. M. Soewandhie Surabaya.
Dari hasil analisa, didapatkan durasi pekerjaan selama 255 hari dan biaya pelaksanaan sebesar Rp 29.724.366.176,84.
======================================================================================================
The preparation of final project entitled Project Schedule and Budget Estimation of Building Type B1 RSUD dr. M. Soewandhie Surabaya with the Half Slab Method which is located on Jl. Tambak Rejo No. 45-47, Tambakrejo, Kec. Simokerto, Surabaya City. This project was built by PT. PP (Persero) Tbk which consists of 2 main buildings, a hospital building with 10 floors and a parking building with 8 floors. However, due to being constrained by COVID-19, this project was only built with 6 floors in the main building and 3 floors in the parking lot.
For this final project, what is being reviewed is the main building of the hospital building from the 1st floor to the roof floor, namely 10 (8 floors +2 roof deck) by modifying the slab that previously used conventional slabs into half slab precast. The work reviewed is only the upper structure. The superstructure includes beam columns, slabs, and stairs, linac rooms, and brachytheraphy using in-situ casting except for slabs that use half slab precast. In the calculation of the time determined by calculating the work, productivity, duration, and resource requirements for each work item. The calculation is adjusted to the appropriate implementation method and references from the relevant literature. Meanwhile, the cost calculation includes material prices, worker wages, and heavy equipment rental prices which are calculated using field prices and references in Surabaya. So it is hoped that the use of the right method will result in effective and efficient time and cost planning in the construction of the Type B1 Building of RSUD dr. M. Soewandhie Surabaya. The final result of this final project is a recapitulation of the calculation of the time and cost of implementation,
vi
as well as the S curve in the Type B1 building construction project at RSUD dr. M. Soewandhie Surabaya.
From the Analysis results, obtained the duration of works is 255 days and the implementation cost is Rp 29.724.366.176,84.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: half slab, Kurva S,biaya,manajemen proyek half slab, S curve, cost, project management
Subjects: T Technology > T Technology (General) > T56.8 Project Management
T Technology > TA Engineering (General). Civil engineering (General) > TA683 Precast concrete construction. Prestressed concrete construction.
T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: Yoga Ferdiansyah
Date Deposited: 02 Sep 2021 07:22
Last Modified: 02 Sep 2021 07:22
URI: http://repository.its.ac.id/id/eprint/90774