Wicahyanto, Choirunoer Julian (2025) Analisis Optimasi Waktu dan Biaya Menggunakan Metode Time Cost Trade Off Pada Proyek Pembangunan Jalan Tol Probolinggo - Banyuwangi Paket 3B. Other thesis, Institut Teknologi Sepuluh Nopember.
![]() |
Text
2035211040-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only Download (29MB) | Request a copy |
Abstract
Tol Probolinggo – Banyuwangi merupakan salah satu bagian dari jaringan Tol Trans Jawa yang terbentang sepanjang 49.68 km dan terbagi menjadi 3 paket. Tugas akhir kali ini membahas paket 3B yang terbentang dari STA 29+600 – 45+800 dengan PT. PP, WASKITA,WIKA KSO sebagai kontraktor dan PT. Parama Karya Mandiri KSO sebagai konsultan pengawas dan memiliki nilai kontrak sebesar Rp4,386,009,017,260.24. Hingga Juli 2024 (Pekan 58), progres dari paket 3B sebesar 39,24% dari target 67,35%. Berdasarkan data tersebut, maka proyek ini mengalami deviasi sebesar 28,11%. Analisis percepatan yang dilakukan pada tugas akhir ini adalah dengan metode time cost trade off menggunakan 3 alternatif percepatan, yaitu penambahan kapasitas alat berat, penambahan shift kerja, dan penambahan tenaga kerja. Ketiga alternatif diterapkan pada pekerjaan yang berada di lintasan kritis sesuai kebutuhan dan dimulai dari cost slope terendah. Analisis percepatan time cost trade off pada proyek Tol Probolinggo – Banyuwangi paket 3B ini diharapkan dapat menghasilkan alternatif baru yang dapat mengatasi keterlambatan dengan biaya tambahan seminimal mungkin. Pasca dilakukkan beberapa iterasi percepatan, iterasi percepatan yang menghasilkan output waktu dan biaya percepatan yang paling optimal adalah iterasi 5 yang menggabungkan 3 alternatif percepatan (penambahan alat berat, shift kerja, pekerja) karena masih memiliki efisiensi waktu yang tinggi, yaitu 14.595% yang mengurangi waktu proyek dari 740 hari menjadi 632 hari serta memiliki efisiensi biaya tertinggi, yaitu sebesar 2.287% yang berhasil mengurangi biaya total proyek dari Rp2,554,538,937,288.39 menjadi Rp2,496,108,986,475.74.
========================================================================================================================================
The Probolinggo–Banyuwangi Toll Road is part of the Trans Java Toll Network, spanning 49.68 km and divided into three construction packages. This final project focuses on Package 3B, which extends from STA 29+600 to STA 45+800, with PT. PP, WASKITA, and WIKA KSO as the contractors, and PT. Parama Karya Mandiri KSO as the supervisory consultant. The contract value for this package is Rp4,386,009,017,260.24. As of July 2024 (Week 58), the progress of Package 3B had reached 39.24%, compared to the target of 67.35%. Based on this data, the project has experienced a deviation of 28.11%. The acceleration analysis conducted in this final project uses the time cost trade off method, employing three acceleration alternatives: increasing the capacity of heavy equipment, adding work shifts, and increasing the workforce. These alternatives are applied to activities on the critical path as needed, starting with the lowest cost slope. The time cost trade off analysis on the Probolinggo–Banyuwangi Toll Road Package 3B is expected to generate viable alternatives to mitigate delays with minimal additional cost. After several acceleration iterations, the most optimal result was found in iteration 5 that combining 3 alternatives (increasing the capacity of heavy equipment, adding work shifts, and increasing the workforce), which achieved a time efficiency of 14.595%, reducing the project duration from 740 days to 632 days. It also yielded the highest cost efficiency of 2.287%, lowering the total project cost from Rp2,554,538,937,288.39 to Rp2,496,108,986,475.74.
Item Type: | Thesis (Other) |
---|---|
Uncontrolled Keywords: | Time Cost Trade Off (TCTO), Percepatan Waktu, Biaya, Manajemen Konstruksi, Ms. Project, Time Acceleration, Cost, Construction Management, Ms. Project. |
Subjects: | T Technology > TH Building construction > TH438 Construction industry--Management. Project management. |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D4) |
Depositing User: | Choirunoer Julian Wicahyanto |
Date Deposited: | 04 Aug 2025 07:19 |
Last Modified: | 04 Aug 2025 07:19 |
URI: | http://repository.its.ac.id/id/eprint/125932 |
Actions (login required)
![]() |
View Item |