Analisis Rework terhadap Biaya pada Proyek Pembangunan Apartemen Gunawangsa Tidar Surabaya dengan Metode Fault Tree Analysis (FTA) dan Expected Monetary Value (EMV)

Saragih, Hansel Samuel Eiros (2017) Analisis Rework terhadap Biaya pada Proyek Pembangunan Apartemen Gunawangsa Tidar Surabaya dengan Metode Fault Tree Analysis (FTA) dan Expected Monetary Value (EMV). Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3113100130-Undergraduate_Theses.pdf]
Preview
Text
3113100130-Undergraduate_Theses.pdf - Accepted Version

Download (3MB) | Preview

Abstract

Pada pelaksanaan proyek konstruksi, besar kemungkinan untuk terjadi rework. Rework merupakan salah satu faktor dalam terjadinya pembengkakan biaya dalam suatu proyek konstruksi, terutama pada proyek high rise building. Oleh karena itu, perlunya diadakan penelitian terhadap biaya akibat faktor-faktor penyebab terjadinya rework.
Objek pada penelitian ini adalah proyek pembangunan Apartemen Gunawangsa Tidar Surabaya, periode 2015-2017. Penelitian diawali dengan mengidentifikasi item-item rework yang terjadi dengan kajian pustaka dan survey lapangan, yang akan ditanyakan melalui interview dan kuesioner kepada beberapa pihak kontraktor yang terlibat (responden). Hasilnya kemudian diolah dengan perhitungan statistik, dikarenakan persepsi setiap responden yang berbeda. Hasil perhitungan statistik akan menunjukkan item-item rework yang paling sering terjadi pada proyek ini. Kemudian dilakukan interview untuk mengetahui faktor-faktor penyebab dari setiap item rework tersebut. Hasil interview kemudian dianalisis menggunakan FTA (Fault Tree Analysis), sehingga diketahui Basic Events dari setiap item rework. Untuk nilai probabilitas (P) setiap Basic Event didapat melalui interview. Probabilitas Basic Event digunakan menghitung probabilitas Intermediate Event dan Top Event. Untuk impact (I) terhadap biaya dari setiap item rework didapat melalui interview maupun NC (Non-Conformance). Probabilitas dan impact tadi digunakan untuk menghitung biaya perkiraan/Expected Monetary Value (EMV) akibat faktor penyebab awal (Intermediate Event tingkat 1) dari setiap item rework.
Kesimpulan dari penelitian ini adalah diketahuinya item-item rework yang sering terjadi pada proyek, yaitu repair kolom/shearwall yang melembung, repair kolom/shearwall yang keropos, repair kolom/shearwall yang retak, dan repair precast facade yang retak gompal. Berdasarkan hasil analisis juga disimpulkan bahwa faktor-faktor penyebab awal dari setiap item rework tersebut, yaitu Faktor Kesalahan Pelaksanaan di Lapangan (Intermediate Event B) dan Faktor Kesalahan Manajerial oleh Site Engineering (Intermediate Event C). Kesimpulan yang terakhir dari penelitian ini adalah diketahuinya biaya perkiraan (EMV) akibat Intermediate Event B dan Intermediate Event C dari setiap item rework tersebut, dimana yang terkecil adalah Rp 20.664,00 dan yang terbesar Rp 510.000,00.

============================================================================================================

In a construction project, it is common that reworks occur.
Rework is one of the factors that could increase the construction
cost, especially
in
the high rise building construction case.
Thus,
in order to minimali
ze these events, it is important to carried out
a research up on costs demand due to
cause factors of rework
.
The object of this research wa
s Gunawangsa Tidar
Apartment Surabaya construction, in 20
15
-
2017 period. This
research was
started by identifying the kind of rework items
which occurred in the co
nstruction site throughout literature
studies and survey, th
at the results will be asked to
some of
th
e
contractor employees (respondents) throughout interviews and
quationnaires. The
answers of the interview and questionnaire
will be processed using statistic calculation due to the different
perception of each
respondent. Based on the calculation before
it’s
shown the most common rework i
tems in this project.
From
those rework items,
t
he causal factors for
each
of them
will be
determine
d
after
. Then, the answers of the interview will be
analyzed using FTA (Fault Tree Analysis). So that, the Basic
Events of each rework item can be obtained. For the probability
(P) of each Basic Event,
will be obtained by the interview. The
probability of the bas
ic events we
re used to calculate the
probability of the Intermediate Event. For the impact (I) of each
rework items will be obtained by the interviews and NC (Non Conformance) files. These pro
ba
bilities (P) and impacts (I) we
re
used to calculate the Expected Monetary Value (EMV) for the
major causes (Intermediate Event lev
el 1) of each rework item
.
Throughout this research were discovered several rework
items that mostly occurred in this construc
tion project which are,
bulging concrete column/shearwall repair, porous concrete
column/shearwall repair, cracked concrete column/shearwall
repair, and cracked facade precast repair.
In addition, the
rework factors such as Poor Implementation Method
(Intermediate Event B) and Poor Site Engineering Managerial
(Intermediater Event C) which known as major causes of those
rework
items
are obtained. And the last result of this research is
obtaining
the EMV of those 2 Intermediate Events, which is the
lowest one
is
Rp 20.664,00
and
the highest one is Rp 510.000,00

Item Type: Thesis (Undergraduate)
Additional Information: RSS 658.404 Sar a-1 3100018074224
Uncontrolled Keywords: Rework, Fault Tree Analysis, Expected Monetary Value
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction > TH437 Building--Cost control.
T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Saragih Hansel Samuel Eiros
Date Deposited: 09 Apr 2018 02:52
Last Modified: 10 Sep 2020 06:23
URI: http://repository.its.ac.id/id/eprint/50500

Actions (login required)

View Item View Item