Perbandingan Sistem Pelat Konvensional dan Precast Half Slab pada Pekerjaan Struktur Atas Ditinjau dari Segi Waktu dan Biaya pada Proyek Caspian Tower Surabaya

Ulya, Yulia Uswatun (2019) Perbandingan Sistem Pelat Konvensional dan Precast Half Slab pada Pekerjaan Struktur Atas Ditinjau dari Segi Waktu dan Biaya pada Proyek Caspian Tower Surabaya. Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 03111745000013-Undergraduate_Theses.pdf]
Preview
Text
03111745000013-Undergraduate_Theses.pdf

Download (14MB) | Preview

Abstract

Peningkatan pembangunan gedung tinggi membutuhkan sistem konstruksi yang efisien. Salah satu contoh gedung tinggi di Indonesia adalah Caspian Tower Surabaya. Sistem konstruksi Caspian Tower Surabaya menggunakan metode konvensional. Sistem konvensional terdapat beberapa kekurangan yaitu membutuhkan waktu yang lama, serta membutuhkan banyak bekisting dan pekerja. Caspian Tower memiliki elemen struktur tipikal sehingga memungkinkan untuk dilakukan sebuah alternatif sistem berupa half slab precast. Sistem precast dapat mereduksi jumlah tenaga kerja dan kebutuhan bekisting sehingga dapat meminimalkan biaya dan waktu pelaksanaan.
Penelitian ini dilakukan untuk membandingkan sistem konvensional dan precast half slab pada proyek Caspian Tower Surabaya dari segi waktu dan biaya. Langkah yang dilakukan adalah penataan site layout, melakukan desain half slab, rotasi bekisting, dan perhitungan waktu dan biaya. Perencanaan waktu menggunakan data produktivitas dari proyek sejenis. Perencanaan biaya menggunakan analisa harga dari proyek sejenis.
Hasil penelitian menunjukkan sistem precast half slab dengan pelat konvensional adalah membutuhkan waktu 288 hari dengan biaya sebesar Rp.72.349.235.235 untuk metode precast half slab sedangkan pelat konvensional membutuhkan waktu 315 hari dengan biaya sebesar Rp.75.355.030.767. Sehingga pada proyek Caspian Tower lebih menguntungkan untuk menggunakan metode precast half slab
==============================================================================================================================
The increase of high building need more efficient construction system. One of high building in Indonesia is Surabaya Caspian Tower. Caspian Tower uses conventional methods. In the implementation of conventional system there are some drawbacks that require a long time, require a lot of formwork and workers. Caspian tower has a typical structural element so it is possible to do an alternative system in the form of half slab precast. The precast system can reduce the amount of labour and formwork needs so as to minimize the cost and time of implementation.
in this research, the author do a comparison of conventional system and precast half slab at Caspian Tower Project in terms of time and costs. The method is structuring site layout, doing half slab design, forwork rotation, and calculation of time and costs. The time planning uses productivity data from similar project. while for cost planning, use price analysis of similar project.
The comparison of precast half slab system with conventional plate tahe 288 days of executing time at cost of Rp.72.349.235.235 for the half slab precast methode while conventional system require implementation time of 315 days at a cost of Rp.75.355.030.767. So that the Caspian Tower project is more profitable to use the precast half slab methode.

Item Type: Thesis (Other)
Uncontrolled Keywords: Pelat Konvensional, Precast Half Slab, Perbandingan Biaya dan Waktu
Subjects: T Technology > TA Engineering (General). Civil engineering (General) > TA683 Precast concrete construction. Prestressed concrete construction.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: YULIA USWATUN ULYA
Date Deposited: 09 Jul 2024 03:04
Last Modified: 09 Jul 2024 03:04
URI: http://repository.its.ac.id/id/eprint/66650

Actions (login required)

View Item View Item