Bendung Bacem adalah Bendung yang terletak di kabupaten Mojokerto Provinsi Jawa Timur. Secara administratif Bendung Bacem terletak di Desa Bening Kecamatan Gondang Kabupaten Mojokerto. Pembuatan Groundsil pada Bendung Bacem di latar belakangi karena terjadinya gerusan pada bagian samping hilir sungai yang menyebabkan runtuhnya bagian revement atau batasan sungai di musim penghujan. Hal inilah yang menjadi penyebab kebutuhan irigasi daerah hilir sungai bendung terhambat.
Secara umum, fungsi pembuatan groundsil pada Bendung adalah untuk mengendalikan ketinggian dan kemiringan dasar sungai, agar dapat mengurangi atau menghentikan degradasi sungai. Bangunan ini juga dibangun untuk menjaga agar dasar sungai tidak turun terlalu berlebihan. Khusus untuk Bendung Bacem, bertujuan untuk meningkatkan kebutuhan air daerah irigasi di Kabupaten Mojokerto
Metode pelaksanaan dibuat untuk memudahkan personil pelaksana proyek dalam mengelola sumber daya yang ada (sumber daya manusia, waktu, material, dan uang). Secara umum, pelaksanaan pekerjaan dimulai dengan pekerjaan persiapan, diantaranya pembuatan kantor direksi, kantor dan gudang kontraktor, barak kerja yang dilengkapi dengan perlengkapan standar. Setelah pekerjaan persiapan dilaksanakan, maka mobilisasi tenaga dan peralatan yang dapat dilaksanakan segera dilakukan dan selanjutnya dilaksanakan pekerjaan fisik yang dapat dikerjakan sesuai dengan sumber daya yang sudah tersedia.
Pada pelaksanaan pekerjaan groundsill ini sangat diutamakan keselamatan kerja pada setiap pekerja baik didalam maupun diluar lokasi terowongan. Pekerja harus menaati semua peraturan yang sudah diterapkan oleh staf K3 untuk menjamin keselamatan pekerja
==============================================================================================================================
Bacem Dam is a weir located in the Mojokerto district of East Java Province. Administratively, Bacem Dam is located in Bening Village, Gondang District, Mojokerto Regency. The making of the Groundsil in Bacem Weir in the background is due to the scouring on the side of the river downstream which causes the collapse of the rejection section or river boundaries in the rainy season. This is the cause of irrigation needs in the lower reaches of the dam river.
In general, the function of making the groundsill in the Weir is to control the height and slope of the riverbed, in order to reduce or stop the degradation of the river. This building was also built to keep the riverbed from dropping too much. Specifically for Bacem Dam, it aims to increase the water needs of irrigation areas in Mojokerto Regency
The implementation method is made to facilitate project executives in managing existing resources (human resources, time, material, and money). In general, the implementation of work began with preparatory work, including the creation of directors 'offices, contractors' offices and warehouses, working barracks equipped with standard equipment. After the preparatory work is carried out, the mobilization of personnel and equipment that can be carried out immediately is carried out and then physical work can be carried out in accordance with the available resources.
In carrying out the work of the groundsill it is very important that work safety be carried out on every worker both inside and outside the river location. Workers must comply with all regulations that have been applied by K3 staff to ensure the safety of workers

Item Type: Thesis (Diploma)
Additional Information: RSIS 627.8 Muh m-1 2019
Uncontrolled Keywords: Implementation Method, Groundsill, Rehabilitation, Mojokerto, Metode Pelaksanaan
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22301-(D4) Diploma 4
Depositing User: Bayu Perwito Sari Nur Muhammad
Date Deposited: 09 Jul 2024 06:14
Last Modified: 09 Jul 2024 06:14
URI: http://repository.its.ac.id/id/eprint/68338

Actions (login required)

View Item View Item