Estimasi Waktu dan Biaya Pelaksanaan Pembangunan Underpass Pasuruan pada Proyek Jalan Tol Gempol-Pasuruan Ruas Grati Seksi 3A STA 21+100 sampai dengan STA 21+525

Rizqi, Moch. Ilham Adi (2020) Estimasi Waktu dan Biaya Pelaksanaan Pembangunan Underpass Pasuruan pada Proyek Jalan Tol Gempol-Pasuruan Ruas Grati Seksi 3A STA 21+100 sampai dengan STA 21+525. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111600000001-Non_Degree.pdf]
Preview
Text
10111600000001-Non_Degree.pdf

Download (4MB) | Preview

Abstract

Tol Gempol – Pasuruan Ruas Grati Seksi 3A merupakan bagian dari Proyek Pembangunan Jalan Tol Gempol – Pasuruan yang menghubungkan daerah Gempol dan Kota Pasuruan. Tol Gempol – Pasuruan memiliki panjang mencapai 34,15 kilometer dan dalam pengerjaannya dibagi menjadi 3 seksi. Seksi I merupakan Ruas Gempol – Rembang dengan panjang 13,9 kilometer dan Seksi II merupakan Ruas Rembang – Pasuruan dengan Panjang 6,6 kilometer. Seksi I dan II telah rampung pengerjaannya dan mulai masing-masing Agustus 2017 dan Juni 2018, sedangkan untuk Seksi III merupakan Ruas Pasuruan – Grati yang sudah rampung dan sudah diresmikan oleh Presiden Joko Widodo.
Dalam Tol Gempol – Pasuruan Seksi III, pengerjaan dibagi kembali menjadi tiga, yaitu Seksi 3A (WIKA), Seksi 3B (PP), dan Seksi 3C (Adhikarya). Yang akan kami angkat dalam tema kami adalah Seksi 3A, yaitu tentang Estimasi Waktu dan Biaya Pelaksanaan Pembangunan Underpass Pasuruan pada Proyek Jalan Tol Gempol – Pasuruan Ruas Grati Seksi 3A STA 21+100 sampai dengan STA 21+525. Pembangunan jalan Tol Gempol - Pasuruan ini dimaksudkan sebagai jalan penghubung altenatif yang menghubungkan kota Gempol dan kota Pasuruan yang sedang bekembang disekitarnya seiring dengan meningkatnya sektor industri dan perdagangan. Dalam pembangunan jalan Tol Gempol Pasuruan seksi 3A ini tentunya selalu memerlukan sumber daya yang berupa tenaga kerja, biaya, bahan, material, dan peralatan. Biaya merupakan salah satu sumber daya yang sangat berperan besar untuk menunjang pembangunan proyek. Maka diperlukan perencanaan terhadap kebutuhan biaya melalui suatu penjadwalan biaya untuk mendapatkan jumlah biaya yang diperlukan berdasarkan waktu pelaksanaan proyek. Di Pasuruan, salah satunya berencana membangun Jalan Tol Gempol - Pasuruan.
=================================================================================================================================
Gempol Toll - Pasuruan Section Grati section 3A is part of the Gempol – Pasuruan toll road development project that connects the Gempol area and Pasuruan city. Gempol Toll – Pasuruan has a length of 34.15 kilometers and is divided into 3 sections. Section I is Gempol – Rembang with a length of 13.9 kilometers and section II is Rembang-Pasuruan with a length of 6.6 kilometers. Section I and II have been completed the process and started each August 2017 and June 2018, while for section III is the Pasuruan section – Grati that has been completed and has been inaugurated by President Joko Widodo. In the toll Gempol – Pasuruan section III, the work is divided into three, namely section 3A (WIKA), section 3B (PP), and section 3C (Adhikarya). What we will raise in our theme is section 3A, which is about the estimated time and cost of implementation of Pasuruan Underpass development on the Gempol toll road project – Pasuruan section Grati sexy 3A STA 21+100 to STA 21+525. The construction of Gempol-Pasuruan Toll road is intended as an alternative link that connects the city of Gempol and the city of Pasuruan which is in the vicinity along with the increasing industry and trade sectors. In the construction of Gempol Pasuruan toll Road Section 3A is certainly always need resources that are in the form of manpower, costs, materials, materials, and equipment. Cost is one of the resources that play a big role to support project development. It is necessary to plan for cost requirements through a scheduling fee to get the required amount based on the time of project execution. In Pasuruan, one of them plans to build Gempol - Pasuruan toll road.

Item Type: Thesis (Diploma)
Additional Information: RSIS 625.7 Riz e-1 2020
Uncontrolled Keywords: Perencanaan, Penjadwalan, Rencana Anggaran Biaya
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction > TH11 Builders' and contractors' bulletins. Including prices, permits, etc.
T Technology > TH Building construction > TH900+ Construction equipment in building construction
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22301-(D4) Diploma 4
Depositing User: Moch. Ilham Adi Rizqi
Date Deposited: 13 Jun 2024 08:49
Last Modified: 13 Jun 2024 08:49
URI: http://repository.its.ac.id/id/eprint/74118

Actions (login required)

View Item View Item