Wardana, Riza Alfian Arief (2020) Model Optimisasi Distribusi dan Perencanaan Terminal Regasifikasi Liquefied Natural Gas (LNG): Studi Kasus Pulau Jawa. Other thesis, Institut Teknologi Sepuluh Nopember.
![]() |
Text
04415440000051-Undergraduate_Thesis.pdf Download (4MB) |
Abstract
Biaya pengapalan LNG yang tinggi mengakibatkan tingginya harga gas yang digunakan sebagai bahan bakar pembangkit listrik. Selain itu, pembangunan unit pembangkitan baru di Cilamaya dan peningkatan kapasitas daya UP Grati mengakibatkan peningkatan permintaan akan LNG. Perencanaan terminal regasifikasi di Jawa Timur diharapkan dapat menunjang pemenuhan kebutuhan akan LNG di UP Gresik dan Grati. Penyedia sarana pembangkit tenaga mengharapkan biaya LNG di Unit Pembangkitan lebih rendah dari nilai 14,5% Indonesian Crude Price (ICP). Permasalahan tersebut akan diselesaikan dengan model optimisasi pendistribusian LNG yang berasal dari 3 (tiga) kilang produksi, yaitu Badak LNG, Donggi Senoro LNG dan Tangguh LNG menuju 3 (tiga) terminal penerima LNG di Jawa. Model optimisasi tersebut menghasilkan 4 pilihan kapal yang digunakan dengan biaya total sebesar Rp34.620.155.621.573 untuk memenuhi permintaan akan LNG yang berjumlah 16.244.803 m3 dan biaya satuan LNG $7,53/MBTU. Perencanaan terminal regasifikasi yang dilakukan menghasilkan dua unit tangki penyimpanan berkapasitas 75.000 m3 dan biaya per tahun sebesar Rp561.191.198.608.
======================================================================================================================================
The high cost of LNG shipping has led to the high price of gas used as fuel for power plants. Also, the construction of a new generation unit in Cilamaya and an increase in the capacity of UP Grati's power have resulted in increased demand for LNG. Regasification terminal planning in East Java is expected to support the fulfillment of LNG needs at UP Gresik and Grati. Power plant providers expect LNG costs in the Generating Unit to be lower than the 14.5% Indonesian Crude Price (ICP) value. This problem will be resolved by optimizing the distribution of LNG from 3 (three) refineries, namely Badak LNG, Donggi Senoro LNG and Tangguh LNG to 3 (three) LNG receiving terminals in Java. The optimization model resulted in 4 choices of vessels used with a total cost of Rp34,620,155,621,573 to meet the demand for LNG totaling 16,244,803 m3 and the unit cost of LNG $ 7.53 / MBTU. The planned regasification terminal has two storage tank units with a capacity of 75,000 m3 and an annual cost of Rp561,191,198,608.
Item Type: | Thesis (Other) |
---|---|
Additional Information: | RSTrL 387.544 8 War m-1 |
Uncontrolled Keywords: | Model Optimisasi, Distribusi LNG, Terminal Regasifikasi |
Subjects: | V Naval Science > V Naval Science (General) V Naval Science > V Naval Science (General) > V220 Naval ports, bases, reservations, docks, etc. |
Divisions: | Faculty of Marine Technology (MARTECH) > Sea Transportation Engineering > 21207-(S1) Undergraduate Thesis |
Depositing User: | Riza Alfian Arief Wardana |
Date Deposited: | 12 Dec 2022 02:00 |
Last Modified: | 21 Mar 2025 00:59 |
URI: | http://repository.its.ac.id/id/eprint/74323 |