Hutomo, Irfananda Setiadi (2021) Penjadwalan Probabilistik pada Proyek Jalur Lintas Selatan LOT. 6. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Text
03111740000011-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only until 1 October 2023. Download (5MB) | Request a copy |
Abstract
Pada umumnya dalam proses perencanaan jadwal proyek dibuat secara manual sehingga hasil penjadwalan dapat terjadi perbedaan dengan desain awal. Hal ini dapat disebabkan oleh tidak dimasukkannya unsur ketidakpastian dalam perencanaan jadwal proyek. Metode yang umum digunakan merupakan metode deterministik dimana hanya memuat 1 durasi proyek saja. Untuk itu diperlukan pendekatan penjadwalan probabilistik yang dapat mengakomodasi ketidakpastian tersebut. Namun hal ini tidak memperhitungkan adanya penambahan durasi akibat kegiatan yang berbentuk paralel. Tujuan utama dari Tugas Akhir ini adalah melakukan penjadwalan probabilistik sebagai alternatif penjadwalan existing yang bersifat deterministik untuk menampung uncertainty pada proyek.
Berdasarkan latar belakang di atas, pada tinjauan kasus Proyek Jalur Lintas Selatan LOT. 6 Provinsi Jawa Timur memerlukan suatu penelitian untuk mendapatkan durasi penyelesaian proyek yang dapat diterima dan probabilitas penjadwalan pada pembangunan proyek tersebut agar mendapat perkiraan waktu yang optimal dan lebih aman. Langkah awal dari penelitian tersebut adalah mencari durasi pekerjaan optimis, paling disukai, dan pesimis hasil survey pada pihak kontraktor dan pihak terkait. Kemudian penelitian juga diilakukan dengan mengumpulkan data-data sekunder yang diperlukan dalam keperluan analisis. Data tersebut digunakan dalam perencanaan lintasan kritis dalam menentukan durasi proyek, dan probabilitas
penyelesaian proyek menggunakan penjadwalan metode PERT. Kemudian data yang berasal dari survey dilakukan simulasi dengan melakukan beberapa kali iterasi dan menggunakan distribusi data Triangular dengan bantuan software.
Berdasarkan hasil perhitungan metode PERT, didapatkan durasi mean penyelesaian proyek sebesar 1036 hari, jauh lebih cepat dibandingkan durasi existing proyek dengan probabilitas penyelesaian sebesar 95,45%, sedangkan untuk probabilitas penyelesaian sebesar 95% didapatkan durasi 1077 hari. Simulasi Monte Carlo dilakukan sebanyak 2000 kali iterasi. Durasi berdasarkan hasil simulasi Monte Carlo yang dijalankan pada penjadwalan proyek pembangunan Jalur Lintas Selatan LOT. 6 untuk rata-rata (mean) selama 1111 hari. Durasi penyelesaian proyek yang menurut hasil simulasi Monte Carlo adalah pada Persentil 95, yaitu 1136 hari. =====================================================================================================
In general, the project schedule planning process is made manually so that the scheduling results can be different from the initial design. This can be caused by not including an element of uncertainty in the planning of the project schedule. The method commonly used is a deterministic method which contains only 1 project duration. However, this does not take into account the additional duration due to parallel activities. The main objective of this research is to perform probabilistic scheduling as an alternative to existing deterministic scheduling to accommodate the uncertainty in the project.
Based on the above background, in the case review of the Trans South Java Project (JLS) LOT. 6 requires a study to obtain an acceptable duration of project completion and the probability of scheduling the project development in order to obtain an optimal and safer time estimate. The initial step of the research is to find the duration of the work that is optimistic, most preferred, and pessimistic of the survey results on the contractor and related parties. Then the research was also carried out by collecting secondary data needed for analysis purposes. This data is used in critical path planning in determining the project duration and the probability of project completion using the PERT methodology. Then the data from the survey is carried out by simulation by generating random numbers and doing several iterations and using the Triangular data distribution with the help of software.
iv
Based on the calculation results of the PERT method, the mean duration of project completion is 1036 days, faster than the duration of the existing project with a completion probability of 95.45%, while the 95% completion probability is 1077 days. The Monte Carlo simulation was carried out for 2000 iterations. The duration is based on the results of the Monte Carlo simulation which was carried out on the scheduling of the The Trans South Java Project LOT. 6 for the mean (mean) for 1111 days. The duration of project completion according to the results of Monte Carlo simulation is at the 95th percentile, which is 1136 days.
Item Type: | Thesis (Undergraduate) |
---|---|
Uncontrolled Keywords: | Penjadwalan Probabilistik, Durasi, penjadwalan deterministik, metode PERT, Simulasi Monte Carlo |
Subjects: | H Social Sciences > HD Industries. Land use. Labor > HD69.T54 Time management. Scheduling T Technology > TA Engineering (General). Civil engineering (General) > TA167.5 Neurotechnology. Neuroadaptive systems T Technology > TH Building construction > TH438 Construction industry--Management. Project management. |
Divisions: | Faculty of Civil, Planning, and Geo Engineering (CIVPLAN) > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | Irfananda Setiadi Hutomo |
Date Deposited: | 06 Aug 2021 09:07 |
Last Modified: | 06 Aug 2021 09:07 |
URI: | http://repository.its.ac.id/id/eprint/85065 |
Actions (login required)
View Item |