Estimasi Biaya Dan Waktu Serta Metode Pelaksanaan Proyek Rehabilitasi Waduk Muara Nusa Dua Kota Denpasar, Bali

Firmansyah, Muhammad Agha (2020) Estimasi Biaya Dan Waktu Serta Metode Pelaksanaan Proyek Rehabilitasi Waduk Muara Nusa Dua Kota Denpasar, Bali. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111500000118-Non_Degree.pdf]
Preview
Text
10111500000118-Non_Degree.pdf

Download (25MB) | Preview

Abstract

Waduk muara nusa dua yang terletak di kota Denpasar,
Bali merupakan salah satu tempat yang memiliki arti penting bagi
masyarakat kota Denpasar. Pasalnya , tujuh sumgai yang berada
dipulau dewata bermuara diwaduk ini.
Kebutuhan sumber daya air dirasakan meningkat, karena
terjadi peningkatan pertumbuhan penduduk dan industri,
khususnya diprovinsi bali yang merupakan daerah dengan
peningkatan industri yang tajam.
Tujuan dibangunnya waduk muara nusa dua adalah untuk
memanfaatkan sumber daya air baku , dan upaya
pengembangannya untuk optimalisasi pemenuhan kebutuhan air
bersih, menampung limpasan air hujan dari daerah pengairan
sungai yang terbuang ke laut setiap waktu sebagai pengendalian
banjir.
Suatu pekerjaan teknik sipil, perlu adanya metode
palaksanaan pekerjaan suatu proyek. Demikian juga padaii
perkerjaan proyek Waduk Muara Nusa Dua Bali, sangat perlu
adanya metode pelaksanaan yang tepat agar proyek tersebut
mendapatkan hasil yang sesuai dengan yang direncanakan.
Dalam pelaksanaan pekerjaan Waduk Muara Nusa Dua
Bali ada beberapa pekerjaan yang kami anggap tidak efisien
sehingga penulis memutuskun untuk menggunakan alat Vibratory
pile driver dan Mobile truck crane agar pekerjaan proyek tersebut
lebih efisien.
======================================================================Muara Nusa Dua Reservoir which is located in Denpasar,
Bali is one of the important and meaningful places for people in
Denpasar. It is mainly because there are seven rivers of the Dewata
Island (Bali) which are all located in this reservoir.
The necessity of water resource is increasing due to the
increase of the industrial and population growth, especially in the
province of Bali which is an area with a significant number of
industrial growth.
The purpose of constructing this reservoir Muara Nusa
Dua is to utilize the raw water resource and also the effort to
develop a more optimize clean water resource’s necessity, to
accommodate rainwater from a river irrigation area which always
streams away to the ocean as a means of flood control.iv
In a civil engineering job, there needs to be an
implementation method of project execution. In the project
execution of Muara Nusa Dua reservoir, there also needs to be a
precise method execution in order to obtain a corresponding result
as planned.
In this Muara Nusa Dua reservoir work execution, there
are some works that are considered as inefficient which lead the
writer to finally decide to use the Vibratory Pile Driver and Mobile
Truck Crane in order to make the project execution works more
efficiently.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Vibratory Pile Driver, Mobile Truck Crane
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: A.Md. MUHAMMAD AGHA FIRMANSYAH
Date Deposited: 31 Aug 2020 03:04
Last Modified: 03 Jan 2024 08:07
URI: http://repository.its.ac.id/id/eprint/81547

Actions (login required)

View Item View Item